Event log for 2018-04-05

  1. 08:45 GT13 started by SGC; FSNL @ 08:57.
  2. 08:57 GT13 synchronized by GCB, load set-point 5 MW; stepwise load increase.
  3. 09:02 GT at 80 MW.
  4. 09:07 Start of electrical tests – reactive power increased to 110 MVar.
  5. 09:14 GT load at 120 MW and start of over-excitation & reactive power tests.
  6. 10:09 GT at base load.
  7. 10:14 Start of AVR droop test (completed at 12:05).
  8. 13:43 Load reduction to 5 MW & load increase to base load (14:08), C-931  (fast gradient).
  9. 14:16 Load reduction to 5 MW & load increase to base load (14:40), C-931  (normal gradient).
  10. 14:46 Load reduction to 5 MW and load increase to 80 MW (15:07).
  11. 16:03 Load rejection to FNSL (GCB opened).
  12. 16:08 GT tripped by flame monitoring protection – intended test.