Event Log for 2018-04-13

GT11:

  1. 08:56 GT11 started by SGC, flame-on @ 09:05.
  2. 09:07 Plant black-out during GT ramp-up and GT trip.
  3. 14:08 GT11 started by SGC.
  4. 14:20 GT synchronized by GCB & stepwise load increase.
  5. 15:05 GT at base load.
  6. 22:26 Load reduction initiated.
  7. 22:53 GT de-synchronized (GCB opened) & GT shut-down.

GT12:

  1. 13:30 GT12 started by SGC.
  2. 13:43 GT synchronized by GCB & stepwise load increase.
  3. 14:42 GT at base load.
  4. 22:16 Load reduction initiated.
  5. 22:33 GT de-synchronized (GCB opened) & GT shut-down.

GT13:

  1. 14:37 GT13 started by SGC.
  2. 14:50 GT synchronized by GCB & stepwise load increase.
  3. 15:58 GT at base load.
  4. 22:55 Load reduction initiated.
  5. 23:18 GT de-synchronized (GCB opened) & GT shut-down.