Event Log for 2018-04-11

  1. 09:10 GT12 started by SGC.
  2. 09:24 GT synchronized by GCB & stepwise load increase.
  3. 10:03 GT @ base load (heat soaking and determination of Pmax).
  4. 13:35 Start of primary frequency response test (100% load point) - C-940.
  5.  14:00 GT @ 142 MW (95% load point).
  6. 14:15 GT @ 120 MW (80% load point).
  7. 14:33 GT @ 105 MW (70% load point).
  8. 14:50 GT @ 90 MW (60% load point).
  9. 15:08 GT @ 75 MW (50% load point).
  10. 15:49 GT load reduced 10 MW.
  11. 15:50 GT de-synchronized (GCB opened) & GT shut-down.