Event Log for 2018-04-06

  1.  08:35 GT13 started by SGC; FSNL @ 08:47.
  2. 08:47 GT13 synchronized by GCB, load set-point 160 MW (fast gradient).
  3. 08:57 GT at base load (158 MW) ⇓ C-916  cold start completed.
  4. Heat soaking & determination of Pmax > prep for primary frequency response tests.
  5. 12:00 Load reduction to 75 MW; 75 MW (50% load) @ 12:07.
  6. 13:35 Load increase to 140 MW; 140 MW (95% load point) @ 13:42 and start of Primary Frequency.
  7. Response Tests C-940.
  8.  14:35 GT @ base load (100% load point).
  9. 14:50 GT @ 120 MW (80% load point).
  10. 15:14 GT @ 105 MW (70% load point).
  11. 15:30 GT @ 90 MW (60% load point).
  12. 15:45 GT @ 75 MW (50% load point).
  13. 16:07 Load reduction to 5 MW.
  14. 16:15 GT de-synchronized (GCB open) & shut-down.