Event Log for 2018-03-26

  1. 09:20 GT11 started by SGC; FSNL at 09:31.
  2. 09:33 GT synchronized by GCB and stepwise load increase.
  3. 10:39 GT at base load (149 MW) > HCO not activated.
  4. 13:00 HCO activated.
  5. 17:00 Load reduction initiated.
  6. 17:17 GT de-synchronized (GCB opened).